Eight Stages of Risk Assessment


scott_owyen_rgb-150x150

by Scott Owyen - Director of Training On Jun 15, 2017, 03:00 AM

Eight Stages of Risk Assessment

With so much changing in the updated ANSI/CSA standards, it is important to call attention to one key item that every user (identified in the standards as employers) needs to be aware of. This includes risk assessment. Here are the eight stages of risk assessment every user must follow under the new standards:

Identify the task to be undertaken

The first stage in the risk assessment is that the task to be undertaken is clearly identified, together with the location and timing.

Select an appropriate MEWP

With so many different types of MEWPs available to choose from, ranging in various rated capacities, working heights and reaches, a user must select an appropriate machine based upon consideration of factors, including — but not limited to — the task to be undertaken, the constraints of the worksite, ground conditions, site access and proximity to the public or other workers.

Assessment of the risks associated with the task

The risks associated with the task specific to a MEWPs’ operations must be identified. These might be associated with the location where the work is to be carried out, the nature of the MEWPs or the personnel, materials and equipment to be carried.

Identify control measures

Once the hazards and risks involved in the task have been identified, the procedures and measures required to control them must be identified and implemented.

Identify safe work procedures

The risk assessment results are used to plan safe work procedures, including any contingencies required, in carrying out the identified tasks.

COPY IMAGE -GS3384RT1-Large-VS-SH-2-1Rescue from height

Rescue planning is a necessary component of a risk assessment when working at height. Some situations require prior planning to ensure a safe and timely rescue.

A system failure of the MEWPs that results in the loss of the platform control functions may be addressed by the use of:

  1. The MEWP auxiliary power function of the controls;
  2. The MEWP secondary manual emergency descent controls.

The user must follow the manufacturer’s directions in the use of these systems. This plan should be included in operator and occupant training.

 A fall from the platform when using a fall arrest system will require a rescue plan to determine how the affected worker will return safely to the platform or ground. The plan must be put in writing and become part of the company's training manual. All occupants must receive training that explains procedures to follow if they fall and await rescue or witness another worker's fall. Ideally this plan will limit the time that an occupant is suspended after an arrested fall.

A rescue plan can include the following:

  1. Self-rescue – by person involved;
  2. Assisted rescue – by other in the work area;
  3. Technical rescue – by emergency services.

As part of the plan, consideration must be given to the rescue of MEWPs’ occupants if the machine is unable to be lowered for any reason, such as complete machine malfunction or work platform entanglement.

In the case of platform entanglement, the operator and occupants must be removed from the platform prior to attempts being made to free the platform. MEWPs which have tipped beyond their center of gravity must be stabilized and secured before attempting rescue. Technical rescue might also be necessary in the event of illness, injury or risk of exposure. Any rescue procedure must take into account the reasons why the platform may be stranded at height and any need for prompt action.

Rescue should always be carried out by appropriately trained personnel, using the machine’s ground controls or secondary lowering system when feasible. All rescue procedures near electrical conductors must comply with section 6.8.11 of the Standard.

Eight Stages of Risk AssessmentCommunicate the Results

The user must communicate the results of the risk assessment to all parties involved.

Review and Adjust

Before a job starts and periodically throughout a long-term job, the risk assessment must be reviewed to check if any parts of the tasks or the working environment have changed and determine the effect that it could have on the safety of the operation. If any modifications to the risk assessment are required, these must be communicated to all those involved prior to resuming the job.

background tile image

Addressing the Challenges of the Upcoming Changes to the ANSI A92 Standards

The upcoming implementation of the new ANSI A92.22 Safe Use and A92.24 Training Standards for Mobile Elevating Work Platforms (MEWPs) in the United States is creating quite a bit of confusion in the industry. T

Continue Reading

...
background tile image

Recap of the Pending ANSI/CSA Standards - Everything is Changing

ANSI (United States) and CSA (Canada) standards have, for almost four decades, provided best practices for safe, reliable access to work at height and have delivered a consistent benchmark for safe machine design in North America.